Status of installation (17.06.08)
|
Status |
Comments |
Tunnel cable network |
All installed and tested |
few re-mountings at positions where monitors were dismounted |
Crates, HV infrastructure |
All installed and tested |
Modifications are ongoing on the crates below the quadrupole magnets, which need all a fixation of the power cords, 70 % needs to be done (status) |
Ionisation chambers |
All installed |
|
SEMs |
About 240, remaining about 40, will be installed July |
One batch of chamber has to be tested in the H4 beam (date 26.06.08) |
Tunnel electronics, CFC |
All installed |
Some test to be done (status) |
Optical fibre |
All installed |
Checks of optical connection are ongoing |
Surface threshold comparator |
Almost all installed |
2 % missing (to be done in the next weeks) (status) |
Combiner cards |
22 cards installed |
Depending on commissioning of BLM – interlock system |
Energy receiver cards (CISV) |
4 IP installed |
|
VME carte cards |
All installed |
status (some fixes to be done) |
|
|
|