BLM meeting
G.Guaglio
8/10
21 Oct 2003
Remarks
‡Proposed actions
‡Improve collimator fixing.
‡Insert the alimentation measurements in the SW.
‡Better uncoupling of the channels to avoid crosstalks.
‡Resolve spikes problem from the source-switch.
‡ 
‡Lessons learnt
‡Reproduce entire measurement set up in house (we lost a lot of time in Louvin trying to fix the collimator better)
‡Radiation could also force the component to extract current signal ( AMPL)
‡It is better to calibrate the amplifier gain after a warm up (channel 2 drift)
‡
‡Files at
‡ 
BLM measurements\Louvain measurements