Status of installation (17.06.08)

 

Status

Comments

Tunnel cable network

All installed and tested

few re-mountings at positions where monitors were dismounted

Crates, HV infrastructure

All installed and tested

Modifications are ongoing on the crates below the quadrupole magnets, which need all a fixation of the power cords, 70 % needs to be done (status)

Ionisation chambers

All installed

 

SEMs

About 240, remaining about  40, will be installed July

One batch of chamber has to be tested in the H4 beam (date 26.06.08)

Tunnel electronics, CFC

All installed

Some test to be done (status)

Optical fibre

All installed

Checks of optical connection are ongoing

Surface threshold comparator

Almost all installed

2 % missing (to be done in the next weeks) (status)

Combiner cards

22 cards installed

Depending on commissioning of BLM – interlock system

Energy receiver cards (CISV)

4 IP installed

 

VME carte cards

All installed

status (some fixes to be done)