LHC BLM threshold modification reports


Questions of auditors


  • Can you give details on how the BLM PCBs have been tested ?

    You can find the details on the following file:
    Validation_production_BLM_electonic_boards.xls


    CFC tests
    1. Step: The PCBs have been test for connectivity and short circuits
    2. Step: All Cards are put in the test bench to calibrate the 1mA point,
    this means all the analogue circuits of the card are tested.
    3. Step: All Cards are put in the test bench to adjust the 10pA, this
    means all the analogue circuits of the card are tested again.
    4. Step: All Cards are put in the test bench for the final test:
    Check: FPGA barcode number, FPGA internal number, Board number
    Verification of the 10pA
    Verification of the 1mA
    Check optical link
    Check of status: TEMP_1 OK, STATUS TEMP_2, STATUS GOH_1 OK STATE, GOH_2
    OK STATE, DAC_OVER_155 OK, DAC_OVERFLOW, POWER SUPPLIES P5V, POWER
    SUPPLIES M5V, POWER SUPPLIES P2V5
    Scan of the HV levels
    Linearity test of the inputs: scan of all channels with 1pA, 10pA, 100pA,
    1nA, 10nA, 100nA, 1uA, 10uA, 100uA, 1mA
    Check of HV-TEST
    Check of the status Level and CRC_ERROR with a negative inout current
    Check of GOH-RST
    Check of DAC-RST
    5. Step: All cards are tested when they have be installed on their final
    place, 10pA check and optical link test.

    Test of tunnel crates and power supplies and  other hardware [excel]

     

  • What is the status of the BLM installation ? Which fraction of BLMs,
    electronics, ... are in their final place ?
    Status
     

  • Can we get input on the experience from the last 2 weeks of running
    the BLMs ? Which type of issues have been discovered ?

    We have not a continuous logging over weeks jet, because the concentrator
    and the measurement database are under development. We have IP6 and IP5
    logging running for the radioactive source measurements.
    Source measurements: 1, 2, 3, 4, 5

    The main issue is actually to get the acquisition system in a stable running mode
    and on the hardware side
    main connector disconnected from the racks, Fiber not plugged
    correct, inside the patch boxes and on the cards.

     

  • Can you provide us with a global schematic showing all parts as well
    as signal paths, dependencies and power supplies/powering/grounding ?

    Some circuit diagrams are shown in the talk of E. Effinger [ppt]
     

  •  Can you send us details on the simulation ? We would like to better
    understand the full picture starting from the initial protons (beam
    loss) up to the current leaving the ionization chamber. How do you
    calibrate ?

         The whole scheme of how we get the final numbers is presented on page 3 of 

         Agnieszka's presentation and on page 4 of  Mariusz's presentation. The most

         complete document describing the simulation chain is study of losses in Triplets,

         but this is a special case because of the interaction debris

         giving a constant contribution to the losses.

 

  • How does a typical signal from a SPS beam loss / HERA beam loss look
    like ? We are in particular interested in the signal vs. time.

          Please look at the last 4 slides of Daniel's presentation, which was updated with some

          examples of fast losses seen by the Ionization Chambers and the FFTs in case of a

          coasting beam. The SEM response to a very fast loss is on the slide 16 compared

          to the (saturated) IC with signal filters.

 

  • Have you compared such a signal with the response from e.g. coupling a
    pulsed signal into the ionization chamber and propagate this signal
    through the full chain ?

    Pulsing the system (discharge of a capacitor),
    we didn't do such a test but there was the injection test and
    we could see signal from the pilot beam. And we pulsed the system in the
    SPS beam dump.

     

  • How are the HV modulation tests working ? What is the frequency and
    the modulated range ?

    You can see 2 slides from the audit presentation
    SLIDE 25: General presentation of the modulation chain (BLECS->HV_PS->IC->BLECF->BLETC->CPU->BLECS)
    SLIDE 45: Presentation of the first results of the modulation and analysis done in 2007, point 8.

    About the
    frequency range I would say 10mHz to 100mHz.
    As you can see in the simulations, in order to have some signal, I guess the minimum frequency should be around 10mHz.
    The maximum frequency is determined by the offset current at the CFC. Because the current to frequency input cannot measure negative current, the modulation contribution to this negative current should not be higher than the offset current at the CFC (max 100pA in test mode). This constraint limits the maximum frequency.
    A second limitation is the readout of the running sum (1Hz) which limits the modulation to 100mHz to have at least 10 point per period.

    The frequencies foreseen have been chosen also after simulations made by Erik VERHAGEN: (
    http://ab-div-bdi-bl-blm.web.cern.ch/ab-div-bdi-bl-blm/Electronics/BLECS_Combiner/BLECS-Simulations/Modulation/SimulModulation.pdf)
    It has been shown that if components are changing over time, we could see:
    At
    30mHz =>       Variation in phase, if the capacitor inside the IC is changing (slide 4).  
    At
    100mHz =>      Variation in gain, if the IC capacitance is changing (slide 5).

    After the first tests, it seems that the
    modulation amplitude will be around 5V peak-to-peak at 1600V offset. The maximum modulation voltage is also linked to the maximum negative input current of the CFC.

  •  Despite you additional document (the MPSC minutes), we would like also
    to deeper understand the entanglement of the master table with the
    disable and mask bits. Can you be more specific ?

           The Master table contains data in a form which correspond to the image in front end

           electronics. It contains maskable / unmaskable and connected/unconnected flags.

           Therefore change of any of these flags is equivalent to change of the Master table

           and this can be done only by Experts. The only think which can be done by "Operators"

           (selected group) is trimming the threshold values.
 


This web site is owned by the account czam


Site created by CERN Web Services on Wednesday, 12 March 2003 at 11:30

Number of hits: .
Send your comments and suggestions concerning this page to Christos Zamantzas